How can I set Project settings to look at both m-f 9-5 and 24/7
Hi Everyone
I have some parts of the business working Monday to Friday 9am-5pm and the manufacturing and quality sides of the business working 24/7. When setting a project plan, can I have the option to set some line items to calculate 24/7 vs M-F?
Thanks
Best Answer
-
You can use Elapsed Time in the duration of specific rows that are assigned to manufacturing and quality to ignore your working days.
For example, instead of 2d as your Duration, add an e in front: e2d
See: Work with Duration and Predecessors
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Answers
-
You can use Elapsed Time in the duration of specific rows that are assigned to manufacturing and quality to ignore your working days.
For example, instead of 2d as your Duration, add an e in front: e2d
See: Work with Duration and Predecessors
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
-
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.5K Get Help
- 468 Global Discussions
- 156 Industry Talk
- 511 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 521 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 307 Events
- 35 Webinars
- 7.3K Forum Archives